Street Construction
2024 Construction Projects
Fourth Street Construction
Updates Coming Soon
Fifth and East South Street Construction
Construction Completed. Punchlist items to be worked on at a later date
Greig Trail and Johnson Street Construction
Construction Completed. Punchlist items to be worked on at a later date
West South Street Reconstruction
*UPDATE*
Tentative Schedule from Contractor
MH castings, cleanup grade/prep for paving binder (bottom layer) – 10-09-24
Sanitary Fixes – 10-09-24 through early next week
Topsoil/Restoration – 10-11-24 and 10-12-24
Finish grading – Wednesday, 10-16-24
Final Surface Paving – Thursday, 10-17-24 and Friday, 10-18-24
Ashberry Lane, Cedarbrook Lane and Stoney Ridge Trail Mill and Overlay Project
Paving to begin on Monday October 7th
Mandt Park Improvements
Questions regarding special assessments, please contact the City of Stoughton Finance Department at 608 873-6677.
WisDOT Majors Project (Stoughton to Mcfarland)- Dane Conty
For more information regarding the DOT project Click Here